Short answer: a workable export claims process has four fixed decision points, in this order: does the failure fall inside the warranty envelope, what is the remedy, who pays which cost line, and what happens to the physical goods. Most claims that go badly wrong skipped the first two and spent their energy arguing about the third. Decide the remedy before anything moves, and the freight argument mostly disappears.
We are an independent trading company. We do not manufacture circuit breakers, contactors or meters, and we are not an appointed distributor for any brand. On the supply side we sit in the middle of these claims: the buyer sends the failure report, the factory holds the warranty analysis, and we are the party who has to make the two match. What follows is how that process actually runs, and where it usually breaks.
Why most claims stall before anyone inspects the goods
A claim arrives as a photograph and a sentence: “the breaker tripped and will not reset”. That is a symptom, not a defect. Before anyone can decide whether the product failed or the application did, four facts are needed: the exact ordering code, the batch or date code, the installation conditions, and what the device was protecting. Without those, a supplier can only answer with a guess, and a guess is what turns a two-week claim into a six-month correspondence.
The single most common stall is a claim raised against a product family rather than a code. A distributor reports “NB1-63 failures” when the field population is three different ratings, two curves and two pole configurations. The factory cannot analyse a family; it analyses a code, and it needs the sample to match that code. If your own records cannot connect the device on the wall to a shipment, the claim is effectively unprovable — not because the supplier is refusing, but because the evidence chain does not exist.
The evidence pack: five items, in this order
Ask for these at the moment the claim is opened, not after the analysis has started. A claim pack that arrives complete is processed in days; one assembled over three emails is processed in weeks.
| Item | What it must show | Why it decides the outcome |
|---|---|---|
| Ordering code and quantity | The code as printed on the device, not as remembered from the invoice | Warranty and certificate coverage are per exact code; a mismatch invalidates the analysis |
| Batch or date code | Production window and, where available, the shipment reference | Separates an isolated incident from a systematic one, and scopes any wider action |
| Failure description | What happened, when, under what load, and whether it repeated | Distinguishes a device defect from a misapplication, which is the most common real cause |
| Application data | System voltage and frequency, load type, upstream protection, ambient conditions | A device used outside its declared envelope is not a warranty case, however new it looks |
| Samples or field evidence | Returned units, or a documented teardown where return is impractical | Failure analysis needs the physical article; photographs rarely settle a dispute |
Decide the remedy before the goods move
There are five remedies and they cost very different amounts. Choosing one late means paying freight twice. Choosing the wrong one means paying freight and still having a dissatisfied customer.
| Remedy | When it fits | Main cost driver |
|---|---|---|
| Repair in destination | Reusable accessory-level faults, or a local service partner exists | Labour and skill, not freight |
| Replacement from stock | Fast-moving modular items where the buyer holds or can hold buffer stock | Double handling, plus the eventual return of the faulty unit |
| Credit note | Low-value items where return freight exceeds the goods value | Documentation discipline — credit without evidence invites repeat claims |
| Scrap in destination with evidence | Bulk failures where re-export is uneconomic or prohibited | Destruction certificate and photographic proof |
| Return to origin | Failures needing real laboratory analysis, or a liability dispute | Freight both ways, duty, and time |
The practical rule: reserve return-to-origin for the cases where the analysis result will change something — a design question, a liability allocation, a batch decision. For routine failures the cheapest correct remedy is almost always replacement or credit with evidence, and the faulty units destroyed or scrapped locally under a documented procedure.
Who pays which cost line
“Who pays the freight” is the wrong question because it bundles four separate costs. Split them and the negotiation becomes concrete: outbound freight, return freight, import duty and taxes on re-import, and the handling or inspection charge at destination. Write the allocation per scenario, not as a general principle.
A conventional split that both sides can live with: the supplier carries replacement cost and outbound freight when the failure is confirmed as a manufacturing defect; the buyer carries return freight to the inspection point; duty and taxes on re-imported goods fall wherever the customs procedure puts them, which is a fact to establish rather than a point to argue. Anything not confirmed as a defect — no fault found, misapplication, damage in transit under the buyer’s Incoterm — stays with the party who owns that risk under the sales contract.
This is why the Incoterm matters twice. It allocates risk at the point of delivery, and it allocates who is the importer of record for any returned goods. A claim on goods shipped under an arrangement where the buyer is the importer of record cannot be resolved by simply sending them back; the return has to be structured as an import.
Re-import, customs and the paperwork trap
Returning goods to China, or to any origin country, is a customs event. Many jurisdictions provide a returned-goods relief or re-import procedure that avoids paying duty a second time, but the conditions are specific: the goods must be identifiable, the re-import must happen within a defined window, and the original export documents must be produced. Miss the window or lose the paperwork and the return becomes a fresh import with full duty and tax.
Two consequences for planning. Keep the export documentation set retrievable for longer than the warranty period, not just the accounting period. And decide, before the first claim, whether returns will be consolidated — a single return shipment covering several claims is far cheaper and much easier to document than five separate small parcels arriving over a quarter.
Batch traceability is built before the failure
Traceability is not a report you can produce afterwards; it is a field you populate at packing. The minimum useful set is the date or batch code on the device, the carton and shipping mark, and the shipment reference that ties the two to an invoice. With that, a claim scopes to a production window in minutes. Without it, every claim becomes a sample-by-sample negotiation.
For low-voltage products there is a second layer: the certificate. A type-test approval is issued for a defined product family and evaluated per exact ordering code, so a claim about a rating or a curve has to be checked against the code that was actually certified. If a private-label or variant project changed anything on the electrical side, the certificate question is part of the claim, not a separate topic.
What to write into the agreement so the process runs
Four sentences in the sales contract remove most of the friction. A warranty period with a defined start trigger — invoice date, shipment date or delivery date, and only one of them. A response obligation: acknowledgement within a stated number of working days, preliminary finding within a stated number, and a named party responsible for each. A remedy hierarchy so replacement is the default for modular items and analysis is the exception. And an evidence list, attached, so nobody argues later about what a complete claim looks like.
The start trigger deserves emphasis because it is quietly the most expensive ambiguity. A warranty measured from invoice date can expire while the goods are still on the water; one measured from delivery date depends on a delivery confirmation that may never be produced. Pick one, write it down, and make sure the buyer’s own downstream warranty to their customers is built on the same clock.
Keeping the claim rate down
Most electrical claims we see are not manufacturing defects. They are an MCB selected on the wrong curve for a motor load, an RCD tripping on cumulative leakage, a contactor sized on AC-1 duty for an AC-3 application, or a device installed in an enclosure that runs far above its reference ambient. None of those are warranty events, and all of them arrive looking like one.
The cheapest claim is the one prevented at specification. That means application questions at quotation stage — system voltage and frequency, load type, upstream protection, ambient, altitude where relevant — and a short commissioning note shipped with the goods. Both cost almost nothing and remove a whole category of dispute. If a buyer cannot answer the application questions, that is itself information worth having before the order, not after.
FAQ
What is the difference between a warranty claim and a quality claim?
A warranty claim says the product failed inside its declared envelope. A quality claim can cover anything from wrong labelling to a packaging defect to a shipment that does not match the ordered code. They follow different evidence paths and often different remedies, so separate them at intake.
Do we have to return faulty units to get a credit?
Not always. For low-value items, a documented destruction or scrap record with photographs is often accepted in place of return, because the freight costs more than the goods. Get that agreed in writing before scrapping, not after.
Who pays freight on a confirmed defect?
Negotiable, but the usual split is supplier bears replacement and outbound freight, buyer bears return freight to the inspection point. Write it per scenario rather than as a general principle, because duty and re-import costs behave differently from freight.
Can a buyer claim against a product family rather than a specific code?
No. Warranty coverage and certification both run per exact ordering code. A claim has to name the code and the batch; a family-level claim cannot be analysed or settled.
How long should we keep export documentation for claims?
Longer than the warranty period plus the re-import window, which in most markets means keeping the full export set for several years. Losing it converts a duty-free return into a fresh import.